Sunday, June 26, 2016

Week 6

The house is coming along very well this week. The framing is now completely closed, the roof has been put on, but exterior doors and windows have yet to be installed. You can see the clear delineation of each room. The electrical is being installed with all the light fixtures and plugs being wired. We have ordered our plumbing fixtures, shower heads, bath, toilets and so on, and those will installed soon.









Below you can see what will become our master bathroom. The picture is taken from the middle bedroom out of 3, and to the left is the separate room where the toilet will be, and behind that will be where the shower and vanity with sink will be. On the right is where the middle bedroom closet is.



One nice feature of having the large pitched roof is a finished attic for storage. We needed to make room for the HVAC unit up there anyway, so our contractor suggested we put in planks that will support weight.





In the middle of the attic is column leading up the skylight in the hallway, and you can see the finished version below (without the window).



Here is the new family room, with Felix using it. Behind him is where the 9 foot French door unit will go. The doors have been ordered and will be arriving soon.



Finally, last Monday was a hot one! The guys were out there roofing in that heat....



Wednesday, June 22, 2016

Week 5

Monday

One huge decision was purchasing the new master bath toilet. I wanted to splurge on a wall-mounted system (the tank is hidden inside the wall), and since it's not very common to use these here in the US other than in commercial properties, this was a big challenge! Doing the research on product ratings and deciphering green building codes (especially in dry California with stringent water use restrictions), has taken a huge amount of my time and given me a lot of anxiety. After many hours of online searching, reading online reviews and personal recommendations, I am so glad to have finally placed my order. If you are unfamiliar with this type of system, you have to get all the pieces separately. Here's what we got: Toto Aquia with matching Toto soft close lid, and Geberit dual-flush tank and frame, and Geberit Sigma 1 flush plate.


Now I have to decide on shower systems. I stopped in at the plumbing supply showroom. Pretty... shiny...!
Then I went to the house to throw some clothes in the machine to find a lovely, airy, open-plan laundry area, although I am sad that they took out the big shelf my dad had put in for us when we bought our house.

Area where the new door from house into garage will go,
located next to the water heater and former workbench area.


Old wall had to be removed to provide frame for new roof.


View from family room.
The big opening is for French doors leading to the patio.

View from garden into family room.
Master bedroom - another set of French doors.
And here are my reasons for coming to the house every night: to feed and check up on the two feral cats who adopted us 7 years ago: Otto's mama Rose and Otto's auntie Rhynose (yes, the kids named them).


 Tuesday

The framing continues...
Starting to build up now, the roof.

The ridge which will be visible from the front.

Thursday

We have a hatch and ladder for the attic access.

The builders have made themselves a temporary drafting table.

Friday

It smells really good now, all the fresh wood joists overhead.


And now we have a 4 x 2 window in the family room as well.

We went to look for bathroom vanities and are still looking for the right kind of patio doors at a fair price.  Our architect came by for her first site visit and approves of the work so far. I have made an appointment with the Department of Water and Power so they can direct where the new electric meter will go.

Monday, June 13, 2016

Week 4

Groundwork is done... now the building begins.

Monday

Delivery!

The rest of the bedroom wall is gone!
The thick blanket of dead leaves and brush is cleared!
MORE wood!
Goofing around in the area that will be the new bathtub

 Tuesday

Huge bales of insulation delivered.
Walls are being framed!

Wednesday

 

Ummmm.... oops? Can't get into the garage anymore, door gone, opening blocked!
And there's no power either so we can't use the clicker for the front...

 

Thursday


The kids'/guest bathroom (rear) and Ella's bedroom

Ella standing in the hallway with the entrance to my bathroom to the left

Standing in front of the master bedroom closet,
looking through to the den/family room

Friday

Today we had a meeting with our contractor to discuss an unexpected issue with the garage entry. The opening for the old one (pictured above) is too small for the new door, which has to be a 6' 8" fire-resistant door in order to be code compliant, so the challenge was to decide where to locate it. There is a water heater, washer & dryer and a workbench along the same wall. The simplest solution seems to be to put the door where the workbench is and demolish the soffit on the kitchen side to give the door some headroom.

We also discussed adding a tankless water heater on the side of the house where the bathrooms are located to save water and energy.

Sunday

We went to the house to do laundry and move the workbenches with tools and other random garage stuff from where the new door will be located. ROADBLOCK! We found the entry again boarded over, now with two large horizontal boards, and when Jim managed to pry them open to get in, we found the washer and dryer had been disconnected and moved out of their alcove. It was unexpected and disappointing to not have been forewarned. We were able to get the front garage door open manually from the inside and Jim got the space cleared. I didn't get before pics but "after" will be posted in next week's update!

Wednesday, June 08, 2016

Week 3

Tuesday


Rebar has been laid.
 

Thursday

 Trenches for the patio footing

Friday

An exciting day...
we stopped by on the way to school to see that
concrete truck had arrived!

Saturday

Voila! Foundation.


 

 Sunday

Giving our new concrete a good soaking to help it set.